POE studied tow methods to install 2.6km-long 6”/10” submarine double insulation pipe between platform WZ11-1N and platform WZ11-1. The study includes pipeline parameter check, onshore pre-fabrication area requirements, pipeline pre-fabrication method, pipeline surface tow method, equipment and pipeline tow calculations.